Water-treatment equipment for Australia
LIFA coordinated tested water-treatment equipment for four Australian plants, all commissioned on schedule with recorded uptime of 99.5%.
- The buyer
- A Perth, Australia regional water utility.
- The product scope
- Water pumps and treatment equipment; 140 units across 4 plants. Program value $3.5M.
What needed to change?
Plant reliability targets demanded certified equipment; the prior procurement's documentation gaps caused commissioning delays at 2 plants.
How LIFA managed the work
We verified AU/NZ standards compliance across all equipment.
We qualified 2 manufacturers with certified test data.
We managed factory acceptance testing per unit.
We structured installation around plant shutdown windows.
All 4 plants commissioned on schedule; uptime 99.5%; the utility renewed at $4.1M for the next maintenance cycle.
From our company project database, with the work, approvals and results shown together.
What this project shows
Factory acceptance testing reduced uncertainty before the shutdown window. Installation planning followed plant availability and the buyer's equipment requirements.