First tranche (8,000 units) delivered by air on the original date; balance delivered within +5 days; penalties limited to €6,000 on one chain; total cost +9% versus the feared +40%.

Four key decisions on this page

Company work archive

Crisis Recovery Apparel Sweden: project record

CRISIS: the fire destroyed 60% of work-in-progress 4 weeks before delivery; penalties were up to €120,000; 2 retail chains threatened delisting.

Buyer and project
A Gothenburg, Sweden apparel brand (~€8M revenue) with a 30,000-unit order in production when the factory suffered a fire.
Products and scope
Ladies' blouses; woven cotton, 30,000 units across 4 styles.

What LifaSourcing.com did

  1. Within 72 hours, verified 5 alternative factories with matching capability and available capacity.

  2. Split the order across 2 factories (18,000 / 12,000 units) to de-risk any single point of failure.

  3. Negotiated priority production slots and 3-shift scheduling to recover time.

  4. Arranged mixed air/sea logistics: 40% airfreight for the first delivery tranche.

  5. Ran full QC (AQL 2.5) at both factories, including re-approval of samples.

Recorded result

First tranche (8,000 units) delivered by air on the original date; balance delivered within +5 days; penalties limited to €6,000 on one chain; total cost +9% versus the feared +40%.

Company record

A proven case study from LifaSourcing.com's historical work archive. The result above records the status reached in this project.

Client identities, supplier contacts and confidential commercial terms are withheld from this public company record.

Discuss your projectAll proven case studies
Ask LIFA AI