Ireland Data Center Cooling

All 64 units passed FAT; zero commissioning failures; both facilities met uptime SLAs from day one; a $3.1M expansion order followed.

Four key decisions on this page

Company work archive

Ireland Data Center Cooling: project record

Cooling performance directly affects uptime SLAs; the prior procurement lacked factory performance testing, causing one unit to fail commissioning.

Buyer and project
A Dublin, Ireland data-center operator expanding two facilities.
Products and scope
Precision cooling units and CRAC systems; 64 units plus controls. Program value $5.9M.

What LifaSourcing.com did

  1. Qualified 2 manufacturers with certified performance test benches.

  2. Ran factory acceptance tests (FAT) on all 64 units.

  3. Managed logistics with shock/vibration monitoring for sensitive electronics.

  4. Coordinated staged commissioning with the site team.

Recorded result

All 64 units passed FAT; zero commissioning failures; both facilities met uptime SLAs from day one; a $3.1M expansion order followed.

Company record

A proven case study from LifaSourcing.com's historical work archive. The result above records the status reached in this project.

Client identities, supplier contacts and confidential commercial terms are withheld from this public company record.

Discuss your projectAll proven case studies
Ask LIFA AI