Solar equipment procurement for Spain
LIFA coordinated solar-module checks and phased equipment deliveries for three Spanish sites, all connected by their deadlines.
- The buyer
- A Barcelona, Spain solar developer with 3 utility-scale sites under construction.
- The product scope
- Solar modules and inverters; 12 MW total capacity; 38,000 modules, 240 inverters. Program value $4.5M.
What needed to change?
Grid-connection deadlines are fixed by the regulator; module quality variance at a prior site caused 2.4% on-site replacement.
How LIFA managed the work
We verified module manufacturers against IEC 61215 and bankability criteria.
We ran electroluminescence sampling on module batches.
We structured phased deliveries to the 3 site construction schedules.
We managed inverter certification (CE, grid-code compliance) per site.
All 3 sites connected on deadline; module quality 99.8%; the developer signed a framework for an additional 9 MW.
From our company project database, with the work, approvals and results shown together.
What this project shows
Batch testing and site-specific documentation needed to progress alongside construction. The three schedules shared suppliers but retained separate connection milestones.
Client identities, supplier contacts and confidential commercial terms are withheld from this public company record.