LIFA client project · Mtwara, Tanzania

Cashew processing equipment for Tanzania.Phase 1 installed in 11 weeks.

A cooperative of 1,100 smallholder farmers needed its first processing line. LIFA matched equipment sourcing to three investment phases, screened ten suppliers and planned delivery through Dar es Salaam. Phase 1 achieved 1.2 tonnes per day of shelling capacity.

The buyer’s challenge

Start processing without buying the whole line at once.

The cooperative could not purchase a complete line in one investment. Its funding arrived in three tranches, while equipment choices had to match cash flow and seasonal nut supply.

No integrated line supplier was available locally. Delivery through Dar es Salaam still needed planning, and intermittent grid electricity made generator-compatible equipment a practical requirement.

The buyer
A cooperative of 1,100 smallholder farmers in Mtwara, Tanzania, establishing its first cashew-processing plant.
The equipment brief
Steam shelling, hot-air drying, grading and vacuum packaging equipment. The full brief specified 1.5 tonnes per day of raw-nut capacity.
How LIFA managed the work

Build each phase around the next practical step.

We linked the equipment shortlist to the cooperative’s investment plan, available power and route into Tanzania. The buyer could approve a defined first phase while keeping the wider line in view.

  1. Structure three investment phases

    We divided the line into three phases matched to cash flow and seasonal nut supply, so the cooperative did not have to fund every stage at once.

  2. Screen ten equipment suppliers

    The comparison covered processing capacity, power requirements and after-sales support.

  3. Plan for the available power supply

    We designed the layout for low power draw and generator compatibility, addressing the intermittent grid supply.

  4. Prepare the import route

    We prepared a customs, freight and clearance plan through Dar es Salaam, including a logistics cost estimate and clearance checklist.

The buyer’s decisions

Approve the plan, then the first purchase.

  • The cooperative board approved the three-phase investment plan.
  • The Phase 1 equipment budget was approved.
  • The equipment shortlist was approved after a capacity review.

The records behind the decision

  • Phased capital-investment plan.
  • Supplier comparison with power and output specifications.
  • Logistics estimate and clearance checklist.

Cooperative identity, investment figures and supplier details are withheld from this public project record.

Completed Phase 1

Equipment installed.
Local processing capacity established.

Phase 1 equipment was sourced and installed in 11 weeks, achieving 1.2 tonnes per day of shelling capacity and creating 34 new jobs. Discussions also opened with two exporters.

Break-even was projected at 14 months. The record does not confirm realized break-even, signed offtake contracts or completion of later investment phases.

Tonnes/day of shelling capacity
Recorded Phase 1 result
1.2
New jobs
Reported for this project
34

What this project shows

A first processing line can be planned around available funding without losing sight of the full process. Capacity, power, supplier support and freight belong in the same purchasing decision. Here, a phased plan turned the first approved investment into installed shelling capacity.

For your next processing-line purchase

Match the machinery to the product and the site.

Define what enters each stage, what must leave it and the conditions the equipment will operate under. For a packing stage, include the product, pouch and seal requirements in the brief.

Cashew-packing equipment illustration with a stainless vacuum chamber, hinged acrylic lid, sealing bar, kernel tray and sealed pouches on a worktable
Capacity with a clear basis
Separate raw-nut input, shelling throughput and finished-kernel output. Ask for operating hours, material assumptions and acceptance-test conditions.
Utilities and support
Confirm available power, backup arrangements, space, maintenance access, spare parts and operator training before comparing machine prices.
The finished pack
Specify kernel grade, pack weight, pouch material and size, seal requirements and expected batch volume. Ask suppliers to demonstrate the proposed combination.

The GIZ/ComCashew equipment-selection guide connects equipment choice with raw materials, utilities, maintenance and technical support. MULTIVAC’s chamber-machine guidance explains why the product, pouch and machine must work together. Use these questions to review the specific offer with your technical team.

Prepare a comparable equipment brief

Make the next quotation useful.

A machine list alone leaves important choices unresolved. Tell suppliers what the line must produce, what the site can support and which phase you intend to buy.

For Tanzania delivery, identify the port, final site and responsibilities for each handover. Have the responsible logistics and clearance providers confirm current requirements for the actual shipment.

Product and process
Raw material, seasonal availability, required process stages, input capacity, target output grades and expected operating hours.
Site and utilities
Layout, available space, electricity specification, backup power, water and any other utilities required by the proposed machines.
Investment and acceptance
Current phase, budget range, future expansion, sample or material trials, performance criteria, training and commissioning responsibilities.
Delivery and after-sales
Destination, target date, packing, freight and clearance scope, spare parts, manuals, warranty terms and the support available after installation.

Support for your processing-line purchase

Explore machinery and industrial-equipment sourcing or sourcing support for Africa.

Before buying a processing line

Cashew-equipment questions, answered.

What did LIFA deliver for the Tanzania cashew project?

LIFA structured a three-phase equipment plan, shortlisted ten suppliers, compared power and output specifications, and planned delivery through Dar es Salaam. Phase 1 equipment was sourced and installed in 11 weeks. The recorded result was 1.2 tonnes per day of shelling capacity and 34 new jobs.

Was the complete cashew-processing line installed?

The confirmed installation covers Phase 1. The wider equipment brief included steam shelling, hot-air drying, grading and vacuum packaging, with a planned raw-nut capacity of 1.5 tonnes per day. The project record does not establish completion of all three investment phases.

Does 1.2 tonnes per day mean finished cashew kernels?

No. The recorded figure is shelling capacity. It should not be described as finished-kernel output or export-ready production. The wider brief specified 1.5 tonnes per day of raw-nut capacity. For a new line, state the input material, process stage, operating hours, output grade and test conditions for every capacity figure.

How did the project address intermittent electricity?

LIFA screened supplier offers for power requirements and designed the equipment layout for low power draw and generator compatibility. For a new project, ask the equipment supplier and your electrical specialist to confirm voltage, phase, running and starting loads, backup-power needs and the machines that must run together.

Did the project achieve its projected financial return?

The record projects break-even in 14 months; it does not confirm that this return was achieved. Discussions opened with two exporters, but these are not recorded as signed offtake contracts. The completed results are the Phase 1 installation, shelling capacity and jobs reported for this project.

Can LIFA work with an equipment supplier we already selected?

Yes. Support can focus on technical quotation comparison, supplier checks, procurement follow-up or shipping coordination. When LIFA finds the supplier, sourcing costs are included in the product quote without an added standard 5% commission. For a customer-provided supplier, the standard service commission is 5% unless agreed otherwise in writing. Equipment, testing, freight and other costs follow the approved scope and quotation.

Review service packages and fees or the sourcing process and buyer approvals.

Start with your process and site

Plan the equipment your next phase needs.

Send your process stages, raw-material and output requirements, available utilities, destination, budget range and target date. Include a layout or supplier quotation if you have one.

We review the brief, clarify missing information and propose a scope for your approval before work proceeds.