Finland Paper Mill Spares: project record
Critical spares took 8-12 weeks; one bearing failure idled a line for 9 days at an estimated $180,000 loss.
- Buyer and project
- A Tampere, Finland paper mill operating 3 production lines.
- Products and scope
- Mill spare parts; rollers, bearings, felts, and wear parts; 1,600 SKUs. Program value $2.0M.
What LifaSourcing.com did
Built the critical-spares list with lead-time targets per SKU.
Consolidated sourcing into 3 manufacturers with certified quality.
Established a consignment stock for 120 critical SKUs.
Negotiated emergency air-freight terms for line-critical parts.
Critical spares lead time 4 weeks; line downtime cut 30%; the consignment stock eliminated 2 potential line idles in year one.
A proven case study from LifaSourcing.com's historical work archive. The result above records the status reached in this project.
Client identities, supplier contacts and confidential commercial terms are withheld from this public company record.