Finland Paper Mill Spares

Critical spares lead time 4 weeks; line downtime cut 30%; the consignment stock eliminated 2 potential line idles in year one.

Four key decisions on this page

Company work archive

Finland Paper Mill Spares: project record

Critical spares took 8-12 weeks; one bearing failure idled a line for 9 days at an estimated $180,000 loss.

Buyer and project
A Tampere, Finland paper mill operating 3 production lines.
Products and scope
Mill spare parts; rollers, bearings, felts, and wear parts; 1,600 SKUs. Program value $2.0M.

What LifaSourcing.com did

  1. Built the critical-spares list with lead-time targets per SKU.

  2. Consolidated sourcing into 3 manufacturers with certified quality.

  3. Established a consignment stock for 120 critical SKUs.

  4. Negotiated emergency air-freight terms for line-critical parts.

Recorded result

Critical spares lead time 4 weeks; line downtime cut 30%; the consignment stock eliminated 2 potential line idles in year one.

Company record

A proven case study from LifaSourcing.com's historical work archive. The result above records the status reached in this project.

Client identities, supplier contacts and confidential commercial terms are withheld from this public company record.