Machinery spare-parts sourcing for Turkey Compatibility before price comparison

LIFA mapped 1,900 machinery parts to models and OEM references for a Turkish buyer, reducing lead time from ten weeks to three.

Four key decisions on this page

Proven client project

Machinery spare-parts sourcing for Turkey

LIFA mapped 1,900 machinery parts to models and OEM references for a Turkish buyer, reducing lead time from ten weeks to three.

The buyer
An Istanbul, Turkey textile mill group maintaining 240 European-made looms and knitting machines.
The product scope
Loom spare parts; needles, sinkers, drive belts, electronic boards; ~1,900 SKUs.

What needed to change?

OEM parts were slow (8-12 weeks) and expensive; aftermarket parts from previous sourcing failed compatibility tests or arrived with wrong tolerances.

How LIFA managed the work

  1. We built a compatibility database: 1,900 SKUs mapped to machine models and OEM numbers.

  2. We verified 6 Chinese parts manufacturers with dimensional and material testing.

  3. We ran 90-day field trials on 120 critical parts.

  4. We negotiated buffer stock for high-failure items.

Project results

Lead time cut from 10 weeks to 3; parts cost −38%; field trial pass rate 94%; machine downtime for parts fell 30% year-on-year.

Proven LIFA project

From our company project database, with the work, approvals and results shown together.

What this project shows

Aftermarket comparisons need dimensional and material evidence tied to machine references. Field trials and buffer stock addressed reliability as well as purchase cost.

Support for a similar project

Share your product specifications, quantity, destination and target date. If you already have a supplier, tell us which part of the order needs support.

Request a project review

Client identities, supplier contacts and confidential commercial terms are withheld from this public company record.